RE18 exam questions are expertly crafted practice tests designed to simulate the real BCS certification exam environment and help you assess your knowledge and figure out where you are lacking. From our free BCS Practitioner Certificate in Requirements Engineering 2018 RE18 practice exam, you will feel secure in passing any question type or time limit. TheExamsLab offers the RE18 exam questions 2024. Don’t settle or do it half-heartedly get the best and invest in the best what you want is what you get.

Page:    1 / 8      
Total 40 Questions | Updated On: Nov 19, 2024
Add To Cart
Question 1

ChemCo Ltd has initiated a project to consider changes in its pension scheme.
Paul works in the marketing department and is enrolled in the pension scheme. He has been invited to
attend a pension scheme project session designed to elicit requirements, understand opinions on the level
of service, and consider how it could be improved in the future. On arrival at the session, Paul recognizes
people from other departments, who are all customers of the pension scheme.
In which type of session is Paul about to participate?


Answer: B
Question 2

Spicer, an herbs and spices company, is building a new website to grow its business online. A meeting is
taking place to prioritize the requirements for inclusion in the first release of the website, which will take
place in July. The second release of the website is planned for September.
Miranda, the company buyer is the owner for a requirement that states: 'The system shall provide screens
for adding new products'. Miranda informs the meeting that new products are added to the system every
three months and that she needs this functionality to be in place before the system goes live. In her view, it
is a mandatory requirement.
Peter, who is developing the system, has stated that he can do a one-off upload of all the products into the
database ready for launch in July, meaning that the website can initially go live without the 'add new product'
functionality.
What priority is Miranda's requirement for the July release?


Answer: B
Question 3

In developing requirements, a business analyst has decomposed requirements to reflect defined goals,
which will deliver some benefit to the customer: the sales manager of Street-Runner Ltd.
The requirements may mostly be achieved in short periods of project effort (2 to 5 weeks), although some
rework and change may be required.
What is the format of these requirements?


Answer: D
Question 4

A project, which was initiated several months ago, has been impacted by the following changes:
1. An organizational restructure has altered the responsibilities of the stakeholders.
2. A new chief executive has been appointed, who has new ideas regarding the immediate focus of the
project.
Which of the following attributes in a requirements catalogue entry would need to be updated to reflect
these changes?


Answer: B
Page:    1 / 8      
Total 40 Questions | Updated On: Nov 19, 2024
Add To Cart

© Copyrights TheExamsLab 2024. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the TheExamsLab.