Question 1

Don is the project manager of the NQP Project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. What document should Don reference for information on the activities and the regulations?


Volume C


Answer: D
Question 2

You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?


Volume B


Answer: A
Question 3

Which of the following individual should respond to the risk with the preplanned risk response?


Volume D


Answer: C
Question 4

A program is in its last year of execution. The program manager will receive a performance bonus if executive
leadership and the program steering committee determine that the program is a success.
How can the program manager justify receiving a performance bonus upon program closure?

Volume D


Answer: C
Question 5

You are the program manager for your organization and are reviewing several proposed change requests for your program. Mary, a stakeholder, who has made a change request is asking why it is taking you so long to review the change. You tell her that you must perform integrated change control to review each change request. What is integrated change control?


Volume B


Answer: A
Page:    1 / 93      
Total 461 Questions | Updated On: Mar 26, 2025
Add To Cart

© Copyrights TheExamsLab 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the TheExamsLab.