×

Special Offer! Sale of the Month | Extra 20% OFF - Ends In Coupon code: TEL20

Free Practice PMI PMP Exam Questions 2025

Stay ahead with 100% Free Project Management Professional PMP Dumps Practice Questions

Page:    1 / 362      
Total 1808 Questions | Updated On: Aug 21, 2019
Add To Cart
Question 1

A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?


Answer: C
Question 2

A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.
Which estimation technique should the project manager recommend?


Answer: C
Question 3

In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.
Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.
What should the project manager do next?


Answer: D
Question 4

A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.
Which measure should mitigate the impact of this key resource's departure?


Answer: C
Question 5

Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.
What should the project manager do?


Answer: C
Page:    1 / 362      
Total 1808 Questions | Updated On: Aug 21, 2019
Add To Cart

© Copyrights TheExamsLab 2025. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the TheExamsLab.