Stay ahead with 100% Free PMI Scheduling Professional PMI-SP Dumps Practice Questions
Robert is the project manager for his organization. Management has asked Robert to provide them with the metric he uses to measure deliverables status, costs incurred, and especially how he measures the schedule progress for schedule adherence. What project component could Robert provide for management?
You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?
You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should you tell management?
Which of the following characteristics of conflict and the conflict management process should be recognized by the project managers while handling conflict in a team environment? Each correct answer represents a complete solution. Choose all that apply.
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure: