×

Special Offer! Sale of the Month | Extra 20% OFF - Ends In Coupon code: TEL20

Why PMI PMI-CP Practice Exam Questions?

Ready to level up your PMI PMI-CP exam study? Just TheExamsLab PMI-CP practice tests free.

PMI-CP exam questions are expertly crafted practice tests designed to simulate the real PMI certification exam environment and help you assess your knowledge and figure out where you are lacking. From our free Construction Professional in Built Environment Projects PMI-CP practice exam, you will feel secure in passing any question type or time limit. TheExamsLab offers the PMI-CP exam questions 2024. Don’t settle or do it half-heartedly get the best and invest in the best what you want is what you get.

Page:    1 / 12      
Total 60 Questions | Updated On: Nov 18, 2024
Add To Cart
Question 1

During the commissioning and startup of a built environment project, two interface stakeholders disagree about their involvement in a recent work incident, accusing each other of dodging responsibility. To avoid such an issue in the future, the construction professional decides to include a RACI matrix in the Interface Agreement (IA). RACI is an acronym for:


Answer: D
Question 2

A construction professional is leading the construction of a new hospital. The project is halfway through its scheduled time frame. The construction professional monitors the scope along with other project constraints, and thinks that, overall, the project seems to be on track. However, some key stakeholders are concerned about potential cost overruns.

What can the construction professional do to address the stakeholders' concerns?


Answer: B
Question 3

Before taking a long leave, a construction professional informed the person filling in for them that they should regularly calculate the project’s Earned Value (EV). Among the following options, what is the right description of an Earned Value?


Answer: C
Question 4

An organization is running a construction megaproject with over 100 interfaces. As it faced some issues in IM implementation, the organization requested the advice of a senior construction professional. After assessing the existing IM implementation, the construction professional recommended the organization to set up a single centralized document to easily review the status of all Interface Agreements (IA).

What document does the construction professional refer to?


Answer: C
Question 5

A senior construction professional works on a nuclear power plant which will be planned and executed using the Advanced work packaging (AWP) approach. After the definition of construction work areas (CWAs), the construction professional moved on to the preparation for the workface planning phase. One of the project planning team wondered about the relationship between the Engineering Work Packages (EWP), the Construction Work Packages (CWP), and the Installation Work Packages (IWP).

What should the construction professional’s answer be? (Select two)


Answer: A,D
Page:    1 / 12      
Total 60 Questions | Updated On: Nov 18, 2024
Add To Cart

© Copyrights TheExamsLab 2024. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the TheExamsLab.