CCP exam questions are expertly crafted practice tests designed to simulate the real Test Prep certification exam environment and help you assess your knowledge and figure out where you are lacking. From our free AACE Certified Cost Professional (CCP) CCP practice exam, you will feel secure in passing any question type or time limit. TheExamsLab offers the CCP exam questions 2024. Don’t settle or do it half-heartedly get the best and invest in the best what you want is what you get.

Page:    1 / 39      
Total 191 Questions | Updated On: Nov 18, 2024
Add To Cart
Question 1

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%. A good description of quantitative data would be as follows:  


Answer: C
Question 2

You are reporting the following Earned Value Analysis information for the project: EV= $1,500,000 AC=$1.000,000 PV= $2,000,000 What is the status of the project?


Answer: C
Question 3


The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses. 9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion?


Answer: D
Question 4

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client. A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%. How does the project stand?


Answer: C
Question 5

You are reporting the following Earned Value Analysis information for the project: EV= $1,500,000 AC=$1.000,000 PV= $2,000,000 What is the status of the project?


Answer: C
Page:    1 / 39      
Total 191 Questions | Updated On: Nov 18, 2024
Add To Cart

© Copyrights TheExamsLab 2024. All Rights Reserved

We use cookies to ensure your best experience. So we hope you are happy to receive all cookies on the TheExamsLab.